Take off a mod bit or built-up roof one layer at a time. Start with the spec's ply count and list each layer in squares: base sheet, interply or ply felts, then cap sheet or flood coat and gravel. Add primer where the substrate needs it. Add the bonding material the application method calls for, in pounds of hot asphalt or gallons of cold adhesive. And count the flashing plies at walls, curbs, and edges as their own lines.
What does a mod bit or BUR takeoff have to list?
Every layer the spec names, each in its own unit, plus the bonding material between layers and the flashing plies. A multi-ply asphalt roof hides quantities inside the ply count. Roll it all into one "membrane, SQ" line and that's where the bid comes up short.
| Line | Unit | Where it comes from in the set | Note |
|---|---|---|---|
| Deck type | Note | Structural sheets | Decides primer and base sheet attachment |
| Vapor retarder (if specified) | SF | Division 07 roofing section | Often missed when it sits in a general note |
| Insulation, by layer and thickness | SF per layer | Roof plan, sections, spec | One line per layer |
| Cover board | SF | Spec, sections | Type and thickness from the spec |
| Tapered insulation and crickets | Flag | Roof plan, tapered layout | Flag for a tapered quote |
| Base sheet | SQ | Division 07 section (07 52 00 for mod bit, 07 51 00 for BUR; confirm on the set) | Attachment method from the spec |
| Ply sheets or interply felts | SQ times ply count | Division 07 section | The line that drops when "4 ply" becomes one line |
| Cap sheet, or flood coat and aggregate | SQ; aggregate in lb or tons per spec | Division 07 section | Gravel surfaced BUR carries both flood coat and aggregate |
| Primer | gal | Spec or manufacturer | Only where called for, for example concrete decks |
| Bonding material | lb of hot asphalt or gal of cold adhesive, by layer | Division 07 section | See Table 2 |
| Base flashing plies at walls and parapets | LF with height | Elevations, sections, details | Height drives material, not just length |
| Curb and penetration flashings | EA with size | Mechanical sheets, details | Size each curb |
| Edge metal and stripping plies | LF by profile | Details | Stripping plies are a separate line |
| Drains and sumps | EA | Plumbing sheets | Check against the roof plan |
| Walkway pads | LF or SF | Roof plan, spec | Often only in the spec |
| Coating (smooth cap with a specified coating) | gal | Division 07 section | Rate from the manufacturer |
How do you turn a ply count into rolls?
Take the roof area in squares, multiply by how many layers of that sheet go down, and divide by the roll's stated coverage. Then add laps and waste.
- Coverage comes from the manufacturer, not the ASTM standard. The product standards (for example ASTM D6222 for APP sheets with polyester reinforcement) set requirements for the sheet, but the coverage per roll is printed on the product's data sheet. GAF's data sheets list RUBEROID 30 and RUBEROID Mop Granule cap sheets at 1 SQ per roll, RUBEROID 20 at 1.5 SQ, GAFGLAS Ply 4 and FlexPly 6 ply felts at 5 SQ, and the GAFGLAS #75 base sheet at 3 SQ. Your specified product may not match, so pull its data sheet.
- Laps vary by product. As one example, a 2010 JM two ply cold process SBS specification (2CID-CA, RS-4286) calls for 3 inch side laps and 6 inch end laps, with end laps staggered at least 3 feet (JM specification, via Sweets). That's one manufacturer's older spec, not a rule; current specs may differ, so check the current one.
- Waste follows layout. See how roll layout drives waste for the general logic.
It helps to know the sheet standards by number when you're reading a spec: SBS sheets fall under ASTM D6162, D6163, and D6164, APP sheets under D6222, D6223, and D6509, and foil surfaced SBS under D6298 (Professional Roofing, Specifying modified bitumen sheet products, January 2019).
Torch, hot mopped, or cold applied: what changes on the takeoff?
The application method is what adds the bonding material lines. The sheets can be nearly the same. What holds them together isn't.
| Method | What the takeoff adds | Where to confirm |
|---|---|---|
| Hot mopped (BUR, and mop grade mod bit base sheets) | Asphalt in pounds per ply; asphalt type; kettle or tanker and fuel; flood coat at the spec's rate | Division 07 section; NRCA quality control guidelines |
| Cold applied | Adhesive in gallons per layer; lap cement or lap adhesive as its own line | Manufacturer spec; ARMA cold adhesive bulletin |
| Torch applied (APP and torch grade SBS) | No field adhesive; flag torch-safe details at combustible substrates and wood nailers, and any spec fire watch requirement | Spec and manufacturer details |
| Self adhered | Primer per manufacturer | Manufacturer data sheet |
Hot mopped. Asphalt applied within 25°F of its equiviscous temperature (EVT) gives a nominal 23 to 25 pounds per ply per 100 square feet, and JM accepts a 25 percent deviation from the listed quantity (JM built-up roofing application guide). Specs often name a target: a United Asphalts BUR guide specification (Section 07510) calls for 25 pounds, plus or minus 20 percent, per 100 square feet (United Asphalts guide spec). The asphalt type (ASTM D312 Type I to IV) follows slope, and that same guide spec requires Type IV above 1/2 inch per foot. ARMA's technical bulletin on BUR asphalt covers the D312 types and EVT.
Cold applied. ARMA gives 1.5 to 2.0 gallons per 100 square feet for interply layers, higher for the first layer over porous substrates, and notes about 1.0 more gallon per 100 square feet over absorptive substrates. JM's SBS and APP specifications give a nominal 1.5 gallons per 100 square feet over nonporous substrates.
Torch applied. The takeoff carries the details, not the safety program: torch-safe details where the substrate or nailers are combustible, and any fire watch the spec requires. GAF notes that APP sheets are typically installed over a BUR base sheet or thermal barrier because many substrates can't be torched directly (GAF asphaltic systems).
Which sheets settle each line besides the roof plan?
- Division 07 sections: system, ply count, surfacing, application method, warranty term.
- Structural: deck type, which drives primer and base sheet attachment.
- Elevations and sections: parapet and wall heights for flashing plies. For wall flashing height, see the parapet membrane takeoff.
- Details: stripping plies at edge metal, curb heights.
- Plumbing: drains and sumps.
- Mechanical: curbs and RTUs.
When the sheets disagree or say nothing, that's an RFI. More on turning gaps into RFIs.
What usually goes on the RFI list for mod bit and BUR?
- The spec says "two or three ply" without naming one.
- Surfacing isn't stated: granulated cap, smooth cap plus coating, or flood coat and gravel.
- Asphalt type isn't named on a sloped area.
- Base sheet attachment over a nailable deck isn't stated.
- The flashing ply count isn't on the detail.
- A re-roof has no core cut or survey. If the warranty term drives the ply count, see warranty requirements on a takeoff.
Worked example (an example, not a real job)
Assumptions: 20,000 SF roof (200 SQ), concrete deck, two ply cold applied SBS (base sheet plus granulated cap), insulation and cover board already counted, 1 SQ rolls for both sheets, waste left as a stated variable.
- Base sheet: 200 SQ ÷ 1 SQ per roll = 200 rolls, before laps and waste.
- Cap sheet: 200 SQ ÷ 1 SQ per roll = 200 rolls, before laps and waste.
- Primer: only if the spec calls for it over concrete. JM lists concrete primer at 1 gallon per 100 SF where a concrete deck needs it (JM SBS specifications): 20,000 ÷ 100 × 1 = 200 gallons.
- Cap interply adhesive at ARMA's 1.5 to 2.0 gallons per 100 SF: 200 × 1.5 = 300 gallons to 200 × 2.0 = 400 gallons. Adhesive for the base layer over the cover board runs higher. Go by the manufacturer.
- Contrast: the same area as a four ply hot BUR at 25 lb per ply per square: 4 × 200 × 25 = 20,000 lb of interply asphalt, before the flood coat.
If the roof sits next to another system, see mixed-system roof takeoffs.
FAQ
How many rolls of modified bitumen do I need per square?
It depends on the product's printed coverage. Many modified bitumen base and cap sheets are 1 SQ per roll, so you need about one roll per square per layer, plus laps and waste.
How much hot asphalt does a BUR take per ply?
Asphalt applied within its EVT range gives a nominal 23 to 25 pounds per ply per 100 square feet, per JM's BUR application guide. One BUR guide spec calls for 25 pounds, plus or minus 20 percent, per 100 square feet.
How much cold adhesive per square for mod bit?
ARMA gives 1.5 to 2.0 gallons per 100 square feet for interply layers, with more over porous substrates.
Is a mod bit takeoff different from a TPO takeoff?
Yes. It has more layers, bonding material by layer, and flashing plies as separate lines. For single ply, see how to price a TPO roof.
Can Sharp Pencil take off a mod bit or BUR plan set?
Yes. You get every layer, ply, primer, bonding material, and flashing ply as its own line in your takeoff workbook, with the source sheet named on every quantity and open items written up as drafted RFIs.
Why send your takeoffs to Sharp Pencil
A takeoff backlog hurts most on the jobs you pass on because nobody has the hours. Here's how we handle the usual headaches.
- Delivered within 48 hours*. A takeoff stuck in a week-long queue does you no good when the bid is due sooner.
- Every quantity names its sheet. Want to check a number? The source sheet is right there.
- No silent blanks. If the drawings can't settle a line, you get a written reason. Not a blank, and not a guess.
- Questions instead of guesses. If the set leaves something open, like a ply count or surfacing the spec never states, you get a drafted RFI. Copy it and send it to the architect.
- Checked before it goes out. Every paid takeoff is checked before delivery.
- Your plans stay yours. Used for your takeoff, never shared, and deleted whenever you ask (automatic deletion after 90 days is being rolled out). See what happens to your plans.
- Monthly plans, with your first takeoff free. $395 per takeoff, or monthly plans: Shop 12 at $2,750/mo, Shop 25 at $5,500/mo, and Shop 60 at $11,000/mo. Your first takeoff is free on a job you're actually bidding.
Our focus is commercial low-slope roofing. Residential is not our focus today, but ask if you have a job in mind. See our commercial roofing takeoff services.
Send us a live bid · See full pricing and plan terms · Or email [email protected]
*Clock starts once any questions we send you are answered.
The Sharp Pencil team
Sources
- NRCA, Quality Control and Quality-assurance Guidelines for the Application of Membrane Roof Systems (Chapter 1, built-up; Chapter 2, polymer modified bitumen): https://industry.nrca.net/eWeb/DynamicPage.aspx?es3_key=fafe1fcc-e7ce-4ef3-8395-742e3d7fcce8&prd_key=26DC302F-F5E2-4ED4-9C59-0FAAEC8A3EF3&site=nrca&webcode=NRCAStorePrdDetails
- NRCA, Specifying modified bitumen sheet products, Professional Roofing, January 2019: https://www.professionalroofing.net/Articles/Specifying-modified-bitumen-sheet-products--01-01-2019/4374
- GAF, Commercial Roofing Products Catalog, Asphaltic Systems: https://www.gaf.com/en-us/document-library/documents/brochures-%26-literature/brochure__commercial_roofing_products_catalog_comgn295.pdf
- GAF, Asphalt roofing solutions: https://www.gaf.com/en-us/roofing-materials/commercial-roofing-materials/asphaltic-membranes/resources
- ASTM D6222: https://www.astm.org/Standards/D6222.htm
- ARMA, Cold adhesive SBS modified bitumen roofing applications: https://www.asphaltroofing.org/cold-adhesive-sbs-modified-bitumen-roofing-applications/
- ARMA, Recommendations regarding built-up roofing asphalt: https://www.asphaltroofing.org/wp-content/uploads/2017/05/Recommendations-Regarding-Built-Up-Roofing-Asphalt_20240220_11_FINAL.pdf
- JM SBS and APP modified bitumen specifications (links above); JM two ply cold process SBS specification (2010, RS-4286; current specs may differ): https://sweets.construction.com/swts_content_files/15415/424188.pdf
- United Asphalts BUR guide specification, Section 07510: https://www.unitedasphalts.com/wp-content/uploads/2012/07/UAS-builtuproofing-Data-Sheet.pdf