How to read a commercial roof plan for a takeoff
What does a commercial roof plan tell the estimator?
Where the roof areas start and stop, which way the water runs, and where drains, scuppers, curbs and edges sit. Some marks change the quantities. Others point to the sheet you need.
Disclosure: Sharp Pencil sells commercial roofing takeoffs, so we have a stake in this topic.
This is a guide to reading a roof plan for quantities, not drainage, code, structural or design advice. The design professional and your bid documents decide those.
This page sticks to the roof plan sheet itself. For the takeoff in order, see how to do a commercial roof takeoff from a plan set. For the rest of the set, see the sheets a roofing takeoff has to read.
It covers low slope plans (TPO, EPDM, PVC, mod bit, BUR) and steep slope plans (standing seam, shingle). The marks below are drafting conventions. Most sets follow them and some don't, so the notes and legend on your own sheet have the final say.
Short answer
A commercial roof plan shows roof areas, slope arrows, drain and scupper locations, curbs and edges. On most sets the notes and legend explain the symbols, so read those first. Then read the marks and follow the section cuts and detail tags to the sheets they name. The plan shows where a condition is. The detail shows what it is.
Start with the scale, the north arrow, the notes and the legend
Read the legend, the general notes and the roof notes before anything else. On most sets that's where the symbols are defined, and often where the roof system is named.
Every firm draws a little differently. A mark means whatever the legend and notes on that sheet say it means.
On most sets the scale is stated on the sheet. Before you measure anything, check that scale against the graphic scale bar or a dimension you know. Printed or reduced sheets are often off scale, and a wrong scale throws off every area and every length you take.
On most sets a north arrow shows how the plan is oriented. Use it to match each side of the roof to the elevations and to keep drain and slope direction straight in your notes.
Roof areas and levels
The roof plan shows where each roof area starts and stops. Measure the field by zone, level and system, and keep each one as its own area.
When the set has more than one roof system, the spec tells you which one goes where. See how to read Division 07 for a roofing takeoff and mixed-system commercial roof takeoff.
Slope arrows
On most sets, slope arrows point downhill, toward the drain, scupper or gutter. The number at the arrow is usually the slope, for example 1/4 inch per foot.
The arrows matter because tapered insulation, crickets and sumps all follow the slope, and the slope off those arrows is one of the things a tapered insulation quote needs from the drawings.
When the set says "tapered insulation by others" or shows slope arrows with no layout, that is a question for the GC, not an assumption.
What the roof plan won't tell you is whether the slope is built into the structure. That's on the structural sheets. If the structure is dead flat, the tapered layout has to make all the slope, which changes insulation volume. See tapered insulation takeoff and the sheets a roofing takeoff has to read.
Drains, scuppers and overflows
The roof plan shows drain and scupper locations as the architect drew them, and each one is a count.
An overflow drain is not a spare. It is a second drain location with its own flashing. Miss one and the takeoff comes up a drain and a drain flashing short.
Overflow scuppers through a parapet add the scupper, the wrap and the edge metal at the face, plus a conductor head and downspout if the elevations show one.
The roof plan may show primary drains only, so check its count against the plumbing sheets. See roof plan counts vs the trade sheets.
The takeoff counts what the drawings show. Sizing stays with the plumbing engineer. For all the lines a drain brings with it, see roof drainage on a commercial takeoff.
Crickets and saddles
A cricket is a small raised, sloped area on the high side of a curb, wall or other obstruction that pushes water around it toward a drain. On most sets it's drawn as a diamond or triangle of hip and valley lines behind the curb or wall, with its own slope arrows that split the flow.
Count and locate each one from the roof plan or the tapered layout so nothing gets missed. Its volume belongs to the tapered insulation quote.
Saddles on the roof plan get counted and located the same way. See tapered insulation takeoff and the commercial roofing estimating glossary.
Curbs, penetrations, hatches and walkway pads
Every pipe, vent, conduit and support that goes through the roof is a count, sorted by flashing type. Curbs get measured by perimeter for the curb flashing, and since skylights, hatches and rooftop units sit on curbs, they count the same way.
Hatches and walkway pads show on the roof plan too, and each one is its own line.
The roof plan can show fewer curbs and penetrations than the mechanical, plumbing and electrical sheets. The items that fill a roof after the units go in can be missing from it altogether. See roof penetrations and curb flashing and roof plan counts vs the trade sheets.
Edge and parapet lines
The roof plan gives you the perimeter and any keyed edge types, so you know where each edge runs and how long it is. It won't give you the profile or the height.
The roof-plan outline is not enough. Edge profiles, face heights, cleats, and transitions live on the detail sheets (and sometimes elevations and specs).
Parapet and wall heights live on the elevations and wall sections. They set the flashing height and the vertical membrane area. The height runs to the termination the detail shows, which is the top of the nailer when there's a nailer and coping. See edge metal takeoff by profile and parapet membrane on a commercial roofing takeoff.
Section cuts and detail tags
On most sets a detail tag is a circle split by a line, with the detail number on top and the sheet it lives on below, for example 3 over A-501.
Section cuts and detail tags are where the roof plan hands you off to the roof details and sections. Those sheets carry the edge, coping, curb, drain, penetration and expansion joint details with their callouts. Skip them and the takeoff misses the actual flashing method and materials for each condition.
The plan shows where a condition is. The detail shows what it is. When the two differ, see what to do when the roof plan and the details conflict.
Reading a steep slope roof plan
On a steep slope plan, ridge, hip, valley, dead valley, rake and eave are each their own linear line, on standing seam and shingle roofs alike. So are endwall and sidewall flashing, transitions, starter, drip edge and gutters.
On most sets, the lines that run level, ridges and eaves, measure true length in plan view. Hips, valleys and rakes usually don't, because they slope. You need the pitch to get their true length, and if you measure one flat off the plan, it comes up short.
Pull slope from the drawings (roof plan notes, elevations, or sections). The field area needs it too. Our glossary puts the basis as plan area × pitch factor for each sloped plane, with the slope taken from the set.
On standing seam, find every standing seam area on the roof plan and note which planes share slope and panel direction. Shingle works the same way without the panel direction: find every shingle area and note which planes share slope.
Panel coverage width, seam type, underlayment, starter and drip edge profile usually live in the spec and details, not as numbers on the roof plan. See standing seam metal roof takeoff and asphalt shingle roof takeoff.
Roof plan marks and what each one changes on the takeoff
| Mark | What it tells you | Takeoff line it changes | Where to confirm it |
|---|---|---|---|
| Scale | How to measure the sheet | Every area and every length | The graphic scale bar or a known dimension |
| North arrow | On most sets, how the plan is oriented | Nothing directly. It lets you match each side of the roof to the elevations and keep drain and slope direction straight in your notes | The roof plan |
| Legend, general notes and roof notes | On most sets, what the symbols mean and often the roof system | The system the quantities are measured for | The roofing spec |
| Roof area outline | Where each roof area starts and stops | Field area by zone, level and system | The roofing spec, when the set has more than one system |
| Slope arrow | Usually the downhill direction, and the slope at the arrow | Tapered insulation, crickets and sumps | The structural sheets and the tapered layout |
| Drain | A drain location as the architect drew it | Drain count and drain flashing | The plumbing sheets and drain schedule |
| Overflow drain | A second drain location | Its own count and its own flashing | The plumbing sheets |
| Scupper | A scupper location | Scupper count, plus a conductor head and downspout if the elevations show one | The elevations |
| Cricket or saddle | A raised, sloped area that turns water toward a drain | Count and location for the tapered insulation quote | The tapered layout |
| Curb | A rooftop unit or fan that sits on a curb | Curb flashing by the perimeter of each curb | The mechanical sheets |
| Pipe or conduit penetration | Something that goes through the roof | Count by flashing type | The plumbing, mechanical and electrical sheets |
| Hatch or skylight | An opening that sits on a curb | Curb flashing by the perimeter of each curb | The roof details |
| Walkway pad | Where walkway pads are drawn | Walkway pads as their own line | The roof notes and the roofing spec |
| Edge line | Where each edge runs and how long it is | Edge metal by profile | The edge details |
| Parapet line | Where the parapet runs | Coping, and vertical membrane up to the termination the detail shows | The elevations, wall sections and parapet detail |
| Section cut | Where the plan points to a section | The condition that section shows | The roof details and sections |
| Detail tag | Usually the detail number and the sheet it lives on | The flashing line for that condition | The detail it names |
| Ridge | On most sets, a level line that measures true length in plan view | Ridge linear feet | The roof plan |
| Eave | On most sets, a level line that measures true length in plan view | Eave linear feet | The roof plan |
| Hip | Usually a sloped line that does not measure true length in plan view | Hip linear feet, with the pitch applied | Slope from the roof plan notes, elevations or sections |
| Valley | Usually a sloped line that does not measure true length in plan view | Valley linear feet, with the pitch applied | Slope from the roof plan notes, elevations or sections |
| Dead valley | A dead valley location | Dead valley as its own line | The flashing details |
| Rake | Usually a sloped line that does not measure true length in plan view | Rake linear feet, with the pitch applied | Slope from the roof plan notes, elevations or sections |
What the roof plan does not show
A takeoff from the roof plan alone tends to get the squares roughly right and miss the counts and heights that drive flashing, labor and accessories.
Heights are on the elevations and wall sections, drain counts on the plumbing sheets, curbs on the mechanical sheets, deck type on the structural sheets, and the system in the spec. See the sheets a roofing takeoff has to read and how to read Division 07 for a roofing takeoff.
Some costs never show up as a measured quantity at all. See the roofing bid lines that are not on the roof plan.
Where Sharp Pencil fits
Send the full plan set and we do the takeoff. It comes back UNPRICED. You put your prices on the quantities and submit the bid.
Pricing is optional. Send your cost data and we apply your prices to the quantities. Any line you have not priced comes back marked UNPRICED.
Four files: START HERE, marked-up drawings PDF, Takeoff.xlsx with a Questions tab, and the material order list.
Every quantity carries its source sheet and its basis.
We take off steep slope (standing seam, shingle) and commercial low slope (TPO, EPDM, PVC, mod bit, BUR) from the full set. See what a roofing takeoff includes.
FAQ
What do the arrows on a roof plan mean?
On most sets, slope arrows point downhill, toward the drain, scupper or gutter. The number at the arrow is usually the slope, for example 1/4 inch per foot. See tapered insulation takeoff.
Does the roof plan show every roof drain?
Not always. The roof plan may show primary drains only, so a count that differs goes on the Questions tab. See roof drainage on a commercial takeoff.
What does a detail tag on a roof plan tell me?
On most sets a detail tag is a circle split by a line, with the detail number on top and the sheet it lives on below, for example 3 over A-501. The plan shows where a condition is. The detail shows what it is.
Can I measure a steep slope roof straight off the roof plan?
Only part of it. On most sets, lines that run level, the ridges and eaves, measure true length in plan view. Hips, valleys and rakes usually do not, because they slope, so you need the pitch to get true length. See standing seam metal roof takeoff and asphalt shingle roof takeoff.
What does a takeoff from Sharp Pencil cost?
$395 per takeoff. $395 covers a new set of drawings, or a new address. First takeoff free, one per contractor, on a job you're bidding or quoting.
What does Sharp Pencil send back?
Four files: START HERE, marked-up drawings PDF, Takeoff.xlsx with a Questions tab, and the material order list. Every quantity carries its source sheet and its basis. Usually within one business day. Delivered within 48 hours*.
*Clock starts once any questions we send you are answered.
Why send it to us
- We take off steep slope (standing seam, shingle) and commercial low slope (TPO, EPDM, PVC, mod bit, BUR) from the full set.
- Every quantity carries its source sheet and its basis.
- Four files: START HERE, marked-up drawings PDF, Takeoff.xlsx with a Questions tab, and the material order list.
- Usually within one business day. Delivered within 48 hours*.
- A plan set you send us will never be used to compete with you, and plan sets are deleted whenever you ask.
- First takeoff free, one per contractor, on a job you're bidding or quoting.
*Clock starts once any questions we send you are answered.
Try it on a job you are bidding
Get your first takeoff free · $395 per takeoff · See a sample takeoff
The Sharp Pencil team