Roof penetrations and curb flashing on a commercial takeoff

By The Sharp Pencil team

Last updated: 2026-11-02.

What does a roof penetration takeoff count?

Pipe and vent flashings by type, pitch pans, curbs for rooftop units, skylights and hatches measured by perimeter, and equipment and pipe supports, each with its unit and source sheet. Any count that differs between the roof plan and the mechanical, plumbing or electrical sheets goes on the Questions tab.

Disclosure: Sharp Pencil sells commercial roofing takeoffs, so we have a stake in this topic.

This is a takeoff checklist, not mechanical, code, structural or warranty advice. The design professional, the manufacturer and your bid documents decide the details.

Short answer

A penetration takeoff counts every pipe, vent, conduit and support that goes through the roof, sorted by flashing type, and measures every curb by its perimeter for the curb flashing. Skylights, hatches and rooftop units sit on curbs, so they count the same way. Each count carries the sheet it came from. Check the mechanical, plumbing and electrical sheets against the roof plan, because they can differ. What the drawings leave open goes on the Questions tab.

What penetration and curb lines does a commercial takeoff carry?

A rooftop unit is not one line. The curb, its flashing and the pipes and conduit around it are each a line.

Table 1. Penetration and curb lines, units and where they come from.
Line Unit Where it usually comes from
Pipe and vent flashings, by size range EA Plumbing and mechanical sheets, roof plan
Pitch pans or sealant pockets EA Roof details, Division 07
Conduit and cable penetrations EA Electrical sheets
Gas piping penetrations EA Plumbing or mechanical sheets
Rooftop unit and fan curbs, by size EA with size Mechanical sheets, roof plan
Curb flashing LF of curb perimeter, as detailed Curb size from the mechanical sheets, curb detail
Skylights EA with size, curb flashing LF Roof plan, architectural details
Roof hatches EA with size, curb flashing LF Roof plan, architectural details
Equipment supports and rails EA Mechanical and structural sheets
Pipe supports and pads EA Mechanical and plumbing sheets, Division 07
Crickets behind curbs Flagged for the taper quote Taper layout or roof plan

For where each count lives in the set, see the sheets a roofing takeoff has to read. For crickets behind curbs, see tapered insulation takeoff.

What does each flashing type add?

The detail sheet decides how each penetration is flashed. The takeoff counts it that way.

Table 2. Flashing types and the lines they add.
Flashing type Lines it adds Where to confirm
Prefabricated pipe boot One boot per pipe, clamp and sealant as detailed Penetration detail, Division 07
Field wrapped flashing Flashing membrane and clamp as detailed, where the detail calls for it Penetration detail
Pitch pan or sealant pocket One pan per penetration or cluster, with sealant as detailed Penetration detail
Curb flashing Membrane up the curb by perimeter, termination and curb cap or counterflashing as detailed Curb detail

On re-roofs, ask whether existing curbs, pans and flashings are removed or reused, and who raises curbs if the new roof is thicker. See commercial re-roof takeoff.

Measure curbs by perimeter

A curb is counted once and flashed all the way around.

The takeoff counts what the drawings show. It does not size curbs or decide flashing heights. That is the design professional's and the manufacturer's call.

Supports, conduit and gas lines

The items that fill a roof after the units go in can be missing from the roof plan.

See roofing bid items that are not on the roof plan.

When the roof plan and the MEP sheets disagree

Count the penetrations twice, once on the roof plan and once on the trade sheets.

Carry the higher count with its source and put the difference on the Questions tab.

See the roofing RFI register.

Worked example

Example data, not a real job.

Assume a 200 ft by 150 ft low slope roof, TPO. The mechanical sheets show 5 rooftop unit curbs, each 8 ft by 6 ft. The roof plan shows 2 skylights, each 4 ft by 4 ft, and 1 roof hatch, 3 ft by 4 ft. The plumbing and mechanical sheets show 18 pipe penetrations with prefabricated boots and 4 irregular penetrations detailed as pitch pans. The electrical sheets show 6 conduit penetrations, and the roof plan shows 4. The mechanical sheets show 10 pipe supports.

Table 3. Worked example lines, units and basis.
Line Quantity Basis
Rooftop unit curbs 5 EA, 8 ft by 6 ft Drawings, mechanical sheets
Skylights 2 EA, 4 ft by 4 ft Drawings, roof plan
Roof hatch 1 EA, 3 ft by 4 ft Drawings, roof plan
Curb flashing 186 LF Curb perimeters
Pipe boots 18 EA Drawings, plumbing and mechanical sheets
Pitch pans 4 EA Drawings, penetration detail
Conduit penetrations 6 EA Drawings, electrical sheets
Pipe supports 10 EA Drawings, mechanical sheets

This set would raise one question: the roof plan shows 4 conduit penetrations and the electrical sheets show 6.

Sources: manufacturer installation guides and published roofing detail guidance.

What you get back from Sharp Pencil

The same penetrations and curbs, counted for you from the full set.

Every quantity carries its source sheet and its basis.

Four files: START HERE, marked-up drawings PDF, Takeoff.xlsx with a Questions tab, and the material order list.

Pricing is optional. Send your cost data and we apply your prices to the quantities. Any line you have not priced comes back marked UNPRICED.

We take off steep slope (standing seam, shingle) and commercial low slope (TPO, EPDM, PVC, mod bit, BUR) from the full set. For the rest of the roof, see TPO roofing takeoff, modified bitumen and built-up roof takeoff and roof drainage takeoff.

See commercial roofing takeoff services and a sample takeoff.

FAQ

What is a roof penetration takeoff?

The part of a roofing takeoff that counts every pipe, vent, conduit, curb, skylight, hatch and support that goes through or sits on the roof, with the flashing lines each one adds, tied to the sheet each count came from.

How is curb flashing measured on a takeoff?

By the perimeter of each curb, in linear feet, from the curb size on the mechanical sheets or the roof plan. If only the unit size is shown, the curb size goes on the Questions tab.

Where do I find the penetration count?

On the mechanical, plumbing and electrical sheets, then the roof plan. The roof plan may show fewer, so a count that differs goes on the Questions tab.

Does the takeoff decide how each penetration is flashed?

No. The details, the design professional and the manufacturer decide the flashing. The takeoff counts each penetration the way the drawings detail it and lists what they leave open.

What does a takeoff from Sharp Pencil cost?

$395 per takeoff. $395 covers a new set of drawings, or a new address. Your first takeoff is free, one per contractor, on a job you're bidding or quoting.

What does Sharp Pencil send back?

Four files: START HERE, marked-up drawings PDF, Takeoff.xlsx with a Questions tab, and the material order list. Every quantity carries its source sheet and its basis. Usually within one business day. Delivered within 48 hours*.

*Clock starts once any questions we send you are answered.

Why send it to us

Residential is not our focus today, but ask if you have a job in mind.